210 Effluent Force Main and Dechlorination Facility
UPDATED: August 14, 2025
Project Start Date: 1-30-2023
Estimated Completion Date: 8-12-2024
The work is located within an approximately 30-foot corridor from the 210 Wastewater Treatment Facility adjacent to the Johnston County Landfill at 680 County Home Road, Smithfield NC 27577 to County-owned property on the Neuse River.
The work consists of the following:
- Installation of approximately 22,600 linear feet of 30-inch effluent force main.
- Installation of approximately 1,100 linear feet of 48-inch effluent gravity outfall.
- New effluent force main headwall.
- Access road from Galilee Road to Neuse River.
- New Dechlorination Building, chemical feed vaults, and emergency generator.


CONTACT
Project Completed On:
June 5, 2026