Four Oaks WWPS and EQ Upgrade

Improving sewage management within the Town of Four Oaks

UPDATED: May 29, 2025

Located in the Town of Four Oaks, the work generally consists of:

  • Constructing a new 880 gpm triplex submersible sewage effluent pumping station wet well with valve vault and flow meter vault.
  • Conversion of the existing pump station into an electrical building.
  • Addition of a sewage grinder in an existing influent wet well.
  • Addition of liquid chemical feed system for odor control.
  • Approximately 100 linear feet of 12- and 16-inch gravity sewer and 40 linear feet of 30-inch diameter bored-and-jacked steel casing at the existing pumping station site.